MP PWD SOR for Electrical Works

The Schedule of Rates sets the department's rate for each item. Understanding how your cost differs from it is the whole of tender pricing.

What the SOR is and what it is not

The Schedule of Rates is the department's published rate for standard items of work. Estimates are built from it, and tenders are usually quoted as a percentage above or below it rather than as item-by-item pricing.

What it is not is your cost. The SOR is built on assumptions about material rates, labour, wastage and overheads at the time it was framed. Your actual cost on a specific site — with its distance, its access, its material sources and today's prices — can be meaningfully different, in either direction.

The contractors who lose money on SOR-based tenders are usually those who quoted a percentage below without working out what their cost actually is on the items that dominate that particular bill.

Where electrical work differs

  • Material is a larger share of cost. Cable, switchgear and fittings dominate, and their prices move faster than the SOR is revised. A quote based on last quarter's copper price can be wrong by the time you deliver.
  • Specification detail matters more. Two items that read similarly in the schedule can differ substantially in what they require. Read the full item description, not the summary line.
  • Testing and commissioning are real costs that get underestimated at bid time.
  • Coordination with civil work affects your programme and therefore your cost, and it is rarely in your control.

Written 5 September 2026. Government requirements and portal behaviour change — message us to confirm before you rely on any date or figure here.

Rate analysis before you quote a percentage

The useful exercise is not analysing every item. It is finding the handful of items that carry most of the bill value and working out your genuine cost on those. If they are comfortably below the SOR, a percentage below is affordable. If they are at or above it, quoting below is buying work at a loss.

This takes a few hours and it is the difference between contracts that make money and contracts that occupy your team for a year and do not. See also our page on the MP PWD SOR and rate analysis generally.

Common questions

The department publishes it and revises it periodically. Always work from the version the tender specifies rather than the one you have on file — using a superseded schedule produces a wrong bid.

Tenders are usually quoted as a percentage above or below. Quoting above is allowed and sometimes correct; whether it wins depends on what others do. Quoting below what you can deliver for never ends well.

Then that item is a loss and the question is whether the rest of the bill carries it. That is exactly the arithmetic to do before bidding, not after.

Yes, for the items that matter. Send us the bill of quantities and we will tell you where the bid is actually decided.